3RD MAINLAND BRIDGE TO BE REPAIRED

by Obeji Eric  |  at  15:17:00

The the repair of third mainland bridge has been inaugurated by the ministers of work on friday 6th July.
The repair is to cost N1.055 billion and is being handled by Messrs Borini Prono & Co (Nig.) Limited. The contract will run from July 6, 2012 to November 5, 2012.
According to the contract papers, the first phase of the replacement of expansion joints will begin on the inward Lagos side between Ebute Meta Interchange and Adeniji Adele. This section will be shut for the duration of the repair work.
The second phase if on the outward Lagos side between Adeniji Adele and Ebute Meta Interchange.